Timeline

Task

Assigned to

Refer to

Target Date

Date Completed

Make Recommendation on whom to partner with

Team

PSLG

7-Dec

15-Nov

Investigate current activity and performance of each group

Howard

 

completed

27-Sep

Investigate policies of each group

Team

 

completed

27-Sep

Collect data: current MIT ILL activity

Christine

 

completed

27-Sep

Collect data: Harvard + BLC direct borrowing 

Pat

 

completed

8-Sep

Investigate costs and benefits associated with each group

Christine

 

15-Oct

15-Oct

Provide analysis of polices and procedures affected

Team

 

15-Oct

1-Nov

Recommend changes to policies and procedures (as needed)

Lacy and Pat

ASG, ISG

15-Oct

7-Dec

Identify internal polices and procedures

Lacy

 

15-Oct

15-Oct

Investigate policies at other institutions 

Lacy

 

completed

20-Sep

Identify conflicts

Lacy

ASG, ISG

15-Oct

15-Oct

Investigate work flows and staffing models at other institutions

Pat

 

31-Oct

8-Nov

Describe staffing models and options  

Pat and Team

 

15-Nov

15-Nov

Identify staffing costs

Team

 

15-Nov

in process

Identify technical, logistical, and other cost challenges

Rich and Team

 

15-Oct

15-Nov

Test URSA and Aleph interoperability

Rich  

STS

2-Nov

Sirsi/Dynix has been contacted, Boston College will be the first Aleph 18/ URSA 4 test site

Investigate authentication options

Rich

STS

2-Nov

Still in process, implementation team will need to investigate

Learn about URSA interface and customization options

Rich

STS

2-Nov

2-Nov

Collect info about how other institutions promote and link to URSA from catalog and library web sites, share with UIG

Rich and Team

UIG

2-Nov

2-Nov

Contact vendors and support contacts at other institutions

Rich

UIG

12-Oct

8-Nov

Identify non-staff costs

Christine

 

12-Oct

8-Nov

Investigate URSA interoperability with ILLiad

Christine

 

completed

21-Sept

Investigate URSA interoperability with SFX

Rich

 

12-Oct

7-Dec

Contact networks to learn about governance, costs, and network wide policies

Howard and Team

 

completed

27-Sept

Schedule site visits/interviews with participating institution(s) similar to MIT to learn about policies, procedures, and challenges

Team

 

12-Oct

12-Oct

Prepare interview questions

Team

 

completed

15-Sep

Complete site visits/conversations with participating institution(s)

Team

 

31-Oct

8-Nov

Update PSLG about project, collect feedback on progress

Team

PSLG

15-Nov

12-Oct, 9-Nov

Share project info with other library staff via brown bag or other meetings

Team

 

2-Nov

URSA team gave presentation during All Public Services staff meeting 30-Nov.

Submit project report to PSLG

Team

PSLG

7-Dec

7-Dec