| Vera/Metalib Implementation timeline | |
May - October 2007 |
|
done |
Selina/Jennifer- populate the Metalib KB with our 40 databases for cross-search |
done |
Nicole - create XHTML templates for Sands, for metasearch search, results, and error screens |
done |
Sands- build the new Vera beta pages |
done |
Alex- order new Metalib & Verde hardware |
done |
Alex- install new Metalib & Verde hardware |
done |
Rich + ExLibris- upgrade to Metalib 4 |
done for now in native interface |
Darcy/librarians- and decide what to do about those databases that have simultaneous user limits |
done |
statistics sub-group of UIG- decide which quantitative stats to gather and how, think through how we'll interpret them |
done- |
show prototype mockups to staff and answer questions |
done |
Rich/Nicole- customize SFX A-Z pages for e-journals |
done |
Nicole - create static html pages for each broad subject, listing the specific subjects |
done |
Nicole - write screens to pop-up from "what am I searching" link |
done |
UIG - come up with set of funny waiting messages |
done |
Nicole - test the alpha version |
done |
Darcy & Nicole do early pre-beta testing of pages... test results from each database, Sands to continue with basic functionality
|
in progress |
Sands/Nicole- make UI changes based on testing results |
done |
release to all-lib for feedback and testing |
done - Aug/Sept. |
UIG- make publicity and communication plan for the new Vera beta, decide where to link to it from, write blog posts, etc. |
done - July 24 |
Nicole - write blog post announcing a new Vera is coming |
done |
Nicole- run a sample export from Vera for listing databases and give to Susan from ExLibris |
done |
Nicole - schedule support plan meeting (below) |
done - August 21 & October 9 |
have meeting with all involved with supporting the new Vera to make support plan |
done |
Nicole- make links to new Vera and update URLs and relevant pages |
November 13 |
***** release beta to the public ******* |
November 13, 2007 - March 2008 |
|
November |
Nicole & UIG- plan usability tests |
December |
Nicole & UIG- conduct usability tests & evaluate results |
January |
Nicole/UIG - make decisions about interface changes based on usability results |
January |
Nicole make mockups of screen changes |
Feb. 1 - March 31 (in progress) |
Sands/Nicole - make usability changes and finish work from before that's still undone |
stage 2 - replace Vera pages that list databases |
|
(in progress) |
librarians - update descriptions of databases in Vera |
(in progress) |
librarians - come up with lists of sub-topics for each Vera subject and make list of which databases belong in those subtopics |
done |
Nicole - mockup page for specific database subject with subcategories |
done |
Rich - test building a page from SFX using Nicole's mockup and manually entered sample data for one subject |
done |
Nicole + UIG - decide which data elements from the old Vera need to show on the screen and in what order |
early April |
Kim/Rich/Nicole - plan the process for exporting data about databases from old Vera and storing it in SFX KB |
early April |
Nicole - build actual page template for listing databases, (include search box for search of both ejs and dbs) |
early May |
import database data from old Vera to SFX (in a test instance) |
early May |
Rich - batchload - using the lists from librarians, enter all the topics and subtopics for each Vera subject into SFX and tag each database with appropriate topics/subtopics |
May |
Rich - using Nicole's page template and stylesheets, build the page template for each subject |
June |
Nicole - test the pages |
June |
Rich - make change and updates |
June |
Kim/Nicole/Rich - make plan for ongoing maintenance and sychronization between old Vera and SFX KB (for databases) |
Nicole + UIG - more testing and evaluation of pages that list dbs - show to all librarians, get feedback |
|
Rich/Nicole - make any more changes needed as a result of feedback |
|
Rich - move pages from sfx_test to sfx_local |
|
Nicole - find more ways to link to and integrate these pages from our web site |
|
Nicole - update shortcut URLs for database subjects |
|
Nicole/Rich/Kim - write documentation for staff |
|
Nicole + UIG - plan for usability tests that include these pages and the rest of Vera Multi-search changes from before |
|
evaluate usability feedback, evaluate stats from Google Analytics and SFX |
|
plan for future updates and changes |
|
Summer 2008 |
|
|
Nicole/UIG: find all places on web site to link to the new Vera Multi find places to embed the search in addition to our home page |
UIG + CFG: marketing and pubicity |
|
Nicole - retire the old Vera public web pages and update all Vera shortcut URLs |
|