ENAV Timeline
The general timeframe for the ENAV project is represented by the table
below. Please note that some dates are approximate.
|
Aug. 15
|
Create group and make announcement to staff
|
Steering Committee
|
Steering Committee approved pilot project, staff were notified,
group was formed
|
|
Oct.25
|
Demonstration to group by Ex Libris
|
Group
|
Complete
|
|
Oct. 25
|
Planning for implementation with Ex Libris
|
Group
|
Complete
|
|
Oct. 5-
Nov. 9
|
Technical planning for implementation - identify/select hardware,
ASP
|
Systems staff team
|
Complete
|
|
Nov. 9
|
Select core resources for initial implementation of MetaLib and
targets for SFX
|
Group
|
Complete
|
|
Nov. 26-27 &
April 30-
May 1
|
Training from Ex Libris
|
Group and
Ex Libris
|
SFX - Complete
MetaLib - Complete
|
|
Nov.-
Mar. 1
|
Modify and enhance user interface
|
Web staff team
|
SFX - In Progress
MetaLib - In Progress
|
|
Nov.-
June 30
|
Select and set up targets, sources and services in SFX
Set up and configure MetaLib resources
Select and set up categories in MetaLib and make recommendations
about relationship with Vera, plan for adding access through library
web pages
Test and modify system
|
Public services staff team, e-resources librarian
and project manager, systems team
|
SFX - In Progress
MetaLib - In Progress
|
|
June 1-15
|
Testing and modifications
|
Group
|
|
|
June 26
|
All-Staff Meeting
|
Group
|
|
|
July 3
|
Report and recommendations for SFX/Metalib
|
Marilyn/Joan
|
|
|
July-Aug.
|
Turn system over to staff
|
Steering Committee
|
|
|
Fall
|
Go live!
|
|
|
|
Fall
|
Usability testing
|
Web Staff Team
|
|
|