Barton Transition
Project Scope
The Project Team is
responsible for:
Communication
- Regularly communicating
with staff about transition issues
- Responding to staff
concerns and questions about the transition process
- Developing a plan
to communicate with users about the transition process
Building relationships
with project partners
- Establishing a
strong working relationship with Ex Libris
- Responding to the
concerns of Ex Libris
- Continuing working
relationship with IS and other MIT staff
Planning
- Developing an
implementation plan with Ex Libris
- Setting deadlines
and insuring that we are in a position to meet deadlines already set
Conversion
- Identifying what
clean-up projects must be completed prior to migration
- Designing the basic
configuration of the installation with Ex Libris
- Determining how
data will migrate into ALEPH (conversion)
- Identifying problem
areas for data conversion with Ex Libris
- Converting as close
to 100% of the data as possible from the Geac ADVANCE system into the
ALEPH 500 system
Testing data and
workflows
- Examining converted
data in the test database
- Testing feeds and
internal workflows
- Working closely
with departments to modify workflows as needed
OPAC Design
- Designing and testing
the OPAC for usability
Training
- Providing training
in technical writing to appropriate staff
- Providing the Ex
Libris training to appropriate staff
- Coordinating systemwide
training in staff modules and the OPAC with the staff trained by Ex
Libris
- Providing Ex Libris
documentation to all staff prior to the live date of 7-1-01
Follow-up
- Following up on
problems between the live date of 7-1-01 and the final acceptance date
of 9-1-01
The Project Team is
NOT responsible for:
- Creating new features
and/or services during the implementation process
- Writing local
documentation concerning ALEPH
|